The Lincolnia Park community is alarmed by Dominion Energy’s plans to build an electrical transmission tower on a field owned by the Lincolnia Park Recreation Club. The utility is threatening to use eminent domain to obtain rights to the property.
Dominion says the project is associated with a proposed substation to serve Starwood Capital’s planned data centers at Plaza 500 on Edsall Road. The Fairfax County Planning Commission is holding a public hearing on the substation on Dec. 2.
Leaders of the Lincolnia Park Civic Association (LPCA) and Lincolnia Park Recreation Club (LPRC) are confused about why their neighborhood is being targeted because the LPRC field, at 6501 Montrose St., is not near Plaza 500 or any substation large enough to serve a data center.
“Thus far, Dominion has not engaged with the community or informed us of their intent,” said LPCA President Karl Ensign. “Instead, Dominion’s communication to LPRC has taken the form of letters threatening eminent domain.”
In July, Jacqulyn Lane, a real estate specialist with Dominion Energy Electric Transmission, sent a letter to LPRC’s post office box stating, “The Company or its agents may need to enter your property for the purpose of making surveys, tests, appraisals, or examinations of the property to determine the suitability of the property for the Project.”
It says “the project” involves building a new substation, new overhead electric transmission structures, and a proposed 100-foot right-of-way, less than one mile long for the Edsall substation. “The Substation Interconnects involve building two new data centers on one site and necessary network upgrades to tie a 176 MW capacity into the Dominion transmission network in Alexandria,” the letter continues. “This station will tap off the 230-kV Line 210 near Van Dorn and extend to the new Edsall Substation.”
Related story: Community members speak out against a substation at Plaza 500
LPRC President Ingrid Torres-McCullough did not sign off on the letter allowing Dominion on the field, which is located between the swimming pool and Holmes Middle School.
The letter informs the LPRC that if they do not give permission, Dominion or its subcontractors will enter their property anyway, as permitted by Virginia Code § 25.1-203. That law allows the use of eminent domain for surveys and testing on private property without permission.
A Dominion contractor subsequently conducted geotechnical and soil resistivity testing next to the volleyball court in the middle of the field.
The State Corporation Commission has already approved a high-voltage transmission line with towers 123 feet tall just 67 feet from homes in the Bren Pointe community that would connect the proposed substation next to the Edsall data centers to the Van Dorn substation. The data center complex is a by-right project and doesn’t need to be approved by the Board of Supervisors.
The only thing that could possibly hold back that project is if the Planning Commission rejects the substation. Lincolnia Park residents are expected to join residents of Bren Mar Park and throughout Fairfax County in speaking out against the substation at the Dec. 2 hearing.

Since the field isn’t near the Edsall Road data center, “we’re having a really hard time figuring out what they want from that property,” said Greg Mariano, a member of the LPCA Executive Board.
“While a transmission route through our neighborhood and LPRC to serve the substation makes little sense to us given the geography, Dominion seems to be seriously considering it,” Mariano said.
It isn’t known whether or how many other monopoles would be constructed in the neighborhood, he says, as “Dominion has not been transparent in their plans.”
Torres-McCullough and Ensign sent a letter to Dominion asking why they are interested in the LPRC property.
“LPRC does not consent to the acquisition of new permanent utility easements, the establishment of a transmission right-of-way, or the installation of any new Dominion electrical infrastructure on our property for this project,” the letter states. “We also oppose new overhead high-voltage transmission lines through the surrounding residential neighborhoods.”
Related story: Planning Commission defers hearing on substation
The Lincolnia Park leaders also reached out to Mason Planning Commissioner Alis Wang and members of the Board of Supervisors seeking more information.
The eight-acre field is used for recreation, sports, and community events, such as an upcoming Halloween parade. Ensign said the civic and recreation associations have been discussing improvement projects for that property for years, including an additional swimming pool for competitions or a soccer field.
He is worried that if a large electrical structure is built there, it would discourage people from joining the pool, which has long been the “heart and soul of the community.” The pool currently has 450 members, but might not survive if a monopole is constructed, Torres-McCullough added.
“Who would want to barbecue, play, and swim under something so threatening? And the high transmission lines to and from this site would travel over our neighborhood as well,” Ensign said.
“We have very real fears we’re trying to get to the bottom of,” he said. “Our beloved recreational facilities and land are now fundamentally at risk for the interests of Dominion.”

If the SCC already approved the lines connecting the BMP substation to the Alexandria substation to the south, why do they need to put lines this far north? When was this northern line approved and by whom? And by what route to they plan to connect this pole to the (not-yet-approved) BMP substation? The most direct route would take them through several parks, protected areas, and established neighborhoods. The approved lines are bad enough, but this is excessive. The county needs to vote down the substation (and stop the data center) and the state needs to block the Dominion merger.
Dominion and it’s threat of eminent domain land grab is unseemly. There is precious little recreational space in the Northern VA. Putting a transmission tower in the middle of one strikes me as being a poor community neighbor. This needs to be piled into the SCC evaluation for the proposed Dom merger with NE.
Presenting the entire use case and alternative analyses is only reasonable.
Perhaps also, the delegates should review Virginia Code § 25.1-203 for possible revision, especially as it pertains to data centers.
This move is an impracticable absurdity and a sign of further bullying tactics to come here and in additional neighborhoods. I have yet to encounter a neighbor who welcomes the Plaza 500 project and it’s increasingly sprawling impingement on our community.
The way to kill this project is for the 5 acre substation that is needed to power the Plaza 500 data center to be rejected. Alexandria has asked Fairfax to reject it. So far, the Fairfax County Planning Commission has just delayed the vote until December 2nd. Delay and deferral is not real action. We need a clear NO vote from the Planning Commission and/or the Board of Supervisors.
This issue is very similar to the issue of the Dominion/NextEra merger. They both relate to Dominion which has a history of being unresponsive to the people, and more interested in their shareholders. Both issues relate to how data centers are driving energy usage and pollution, and driving power transmission lines like this. Both need and clear and strong NO, but so far both have just gotten delays, pushing back the decision that needs to be made. We will not have control of our community and our environment until we have the resolve to tell Dominion NO. No to strong-arming a community pool into a transmission tower, no to the substation and resulting Plaza 500 data center, and no to the energy company merger that will cost us in the long-run.
Paul Gilbert
Rather than opposing the project outright, why not explore a solution in which only the necessary land is acquired and meaningful upgrades are made to the pool and other community facilities as part of the agreement? Many of these assets are aging and would benefit from modernization. Furthermore, much of the information being circulated has yet to be verified, making it difficult to assess the proposal objectively. From my perspective, some of the reaction appears driven more by concern and speculation than by established facts. Given that both local communities and the nation are already behind in expanding critical power infrastructure, it is especially important that the discussion remain focused on verified information and practical solutions.
They are delaying until after the elections
I hope December 2nd everyone can come out and support Vote NO for a Monopole!
Didn’t Dominion also scuttle the Lake Accotink project —. Really lousy community engagement for a public utility/monopoly
How does LPRC or LPCA benefit from this proposed tower? How does anyone in the wider community benefit from this proposal? Does Dominion run the Commonwealth? Please tell the community why the only people that benefit from this is Dominion. Not it’s residential customers or small businesses in the community.
I was led to believe that a property could not be taken by eminent domain if it will be used for profit. I know I voted for this law years ago when the Boat House in Old Town was threatened by the then-mayor.
I thought the Edsall Road data centers were being rejected? I want to know exactly why we need more data centers. Is it for more national security info storage or for more sophisticated/invasive advertising to all of us? Why exactly do we need all this data, what is being collected and for what ultimate uses? Just keeping up with China isn’t a good enough reason.